28 September 2023

B block final floor concrete molds are being removed. C Block 4th floor concrete molds are being prepared.

//

13 April 2023

Avalon Garden floors begin to rise. A, B and C Block floor concrete continue to be made.

//

22 March 2023

Groundbreaking for Avalon Gardens Block A, Block B and Block C. A and B Block floor concrete continues to be made.

//

28 February 2023

The foundations of Avalon Gardens Block A, Block B and Block C have been completed. A Block floor concrete has started to be made.

//

24 December 2022

The foundation excavations of the Avalon Garden Project were completed and construction began.